TIMELINE FOR ISSUANCE OF SALES TAX EXEMPTION CERTIFICATE

ON IMPORT OF RENEWABLE ENERGY EQUIPMENT

        
S. No. Task/Activity Timeline
1. Request of company received and forwarded to PV Off-Grid section 1 – 2 days
2. Scrutiny of company’s documents 1 – 2 days
3. Processing of Case 2 – 3 days
4. Approval of Case 2 – 3 days
5. Issuance of Exemption Certificate 1 – 2 days
Total Number of Days 7 – 12 days

 

Reference:

  1. Sales Tax Exemption Certificate is issued to the importers of Renewable Energy Equipment under the provision of serial no. 110 of Table-I of the 6th Schedule of Sales Tax Act 1990.
  2. In case if there are shortcomings, they are communicated to the company for addressing and submitting in 2-3 days.
  3. Days mean working days.

 

   