CURRENT STATUS OF WIND POWER PROJECTS

AEDB is pursuing 40 Wind power projects of cumulative capacity of approximately 2010.2 MW.

1. Twenty-Four (24) wind power projects of 1235.20 MW cumulative capacity have achieved Commercial Operation and are supplying electricity to National Grid:

 

  Name of Project Capacity Location COD
1 FFC Energy Limited  49.5
Jhampir, Dist. Thatta 16 May, 2013
2 Zorlu Enerji Pakistan (Pvt.) Ltd  56.4 Jhampir, Dist. Thatta 26 Jul, 2013
3 Three Gorges First Wind Farm Pakistan (Pvt.) Limited  49.5 Jhampir, Dist. Thatta 25 Nov, 2014
4 Foundation Wind Energy – II Ltd. 50 Gharo, Dist. Thatta 10 Dec, 2014
5 Foundation Wind Energy – I Ltd. 50 Gharo, Dist. Thatta 11 Apr, 2015
6 Sapphire Wind Power Company Ltd 52.8 Jhampir, Dist. Thatta 22 Nov, 2015
7 Yunus Energy Ltd. 50 Jhampir, Dist. Thatta 16 Sep, 2016
8 Metro Power Company Ltd. 50 Jhampir, Dist. Thatta 16 Sep, 2016
9 Tapal Wind Energy Pvt. Ltd. 30 Jhampir, Dist. Thatta 7 Oct, 2016
10 Tenaga Generasi Ltd. 49.5 Gharo, Dist. Thatta 11Oct, 2016
11 Master Wind Energy Pvt. Ltd. 52.8 Jhampir, Dist. Thatta 14 Oct, 2016
12 Gul Wind Energy Ltd 50 Jhampir, Dist. Thatta 18 Oct, 2016
13 Hydro China Dawood Power Pvt. Ltd. 49.5 Gharo, Dist. Thatta 5 Apr, 2017
14 Sachal Energy Development Pvt. Ltd. 49.5 Jhampir, Dist. Thatta 18 Apr, 2017
15 United Energy Pakistan Pvt. Ltd 99 Jhampir, Dist. Thatta 16 Jun, 2017
16 Hawa Energy Pvt. Limited 49.6 Jhampir, Dist. Thatta 15 Mar, 2018
17 Jhampir Wind Power Limited 49.735 Jhampir, Dist. Thatta 16 Mar, 2018
18 Artistic Energy Pvt. Ltd. (formerly Hartford Energy Pvt. Limited) 49.3 Jhampir, Dist. Thatta 16 Mar, 2018
19 Three Gorges Second Wind Farm Pvt. Ltd. 49.5 Jhampir, Dist. Thatta 30th Jun, 2018
20 Three Gorges Third Wind Farm Pvt. Ltd. 49.5 Jhampir, Dist. Thatta 9th Jul, 2018
21 Tricon Boston Consulting Corporation Pvt. Limited (A) 49.6 Jhampir, Dist. Thatta 16 Aug, 2018
22 Tricon Boston Consulting Corporation Pvt. Limited (B) 49.6 Jhampir, Dist. Thatta 14 Sep, 2018
23 Tricon Boston Consulting Corporation Pvt. Limited (C) 49.6 Jhampir, Dist. Thatta 11 Sep, 2018
24 Zephyr Power (Pvt.) Ltd 50 Gharo, Dist. Thatta 27 Mar, 2019
 
2. Twelve (12) wind power projects of 610 MW capacity have achieved Financial Closing and are under construction:
 
  Name of Project Capacity Location Financial Closing Date
1 Lakeside Energy (Pvt.) Ltd. 50 Jhampir, Dist. Thatta 18 Nov, 2019
2 Artistic Wind Power (Pvt.) Ltd. 50 Jhampir, Dist. Thatta 18 Nov, 2019
3 Liberty Wind Power 1 (Pvt.) Limited 50 Jhampir, Dist. Thatta 18 Nov, 2019
4 Indus Wind Energy Limited 50 Jhampir, Dist. Thatta 18 Nov, 2019
5 Act2 Wind (Pvt.) Limited 50 Jhampir, Dist. Thatta 18 Nov, 2019
6 Metro Power Company Ltd. 60 Jhampir, Dist. Thatta 18 Nov, 2019
7 Liberty Wind Power 2 (Pvt.) Ltd. 50 Jhampir, Dist. Thatta 18 Nov, 2019
08 Master Green Energy Ltd. 50

Jamshoro Dist.

18 Nov, 2019
09 Gul Ahmed Electric Limited 50 Jhampir, Dist. Thatta 18 Nov, 2019
10 Din Energy Limited 50 Jhampir, Dist. Thatta 18 Nov, 2019
11 Nasda Green Energy (Pvt.) Ltd. 50 Jhampir, Dist. Thatta 18 Nov, 2019
12 Tricom Wind Power (Pvt.) Ltd. 50 Jhampir, Dist. Thatta 18 Nov, 2019
 
3. Four (04) wind power projects of 165 MW capacity are at different stages of project development:
 
S# Name

Capacity

(MW)

Location
1 Western Energy Pvt. Limited 50 Jhampir, Dist. Thatta
2 Burj Wind Energy Pvt. Limited 14 Gujju, District Thatta
3 Shaheen Foundation 51 Jhampir, Dist. Thatta
4 Trans Atlantic Energy Pvt. Ltd. 50 Jhampir, Dist. Thatta

In light of Covid-19 outbreak AEDB disinfected its Head Office