PROCESS SCHEDULE FOR ISSUANCE OF NET METERING CERTIFICATE TO DOMESTIC/FOREIGN INVESTORS UNDER AEDB CERTIFICATION REGULATIONS (2018)
S.No. | Task/Activity | Time Line |
01 | Receipt of company proposal at AEDB | |
02 | Forwarding of proposal to relevant Section of AEDB from CEO Secretariat | 01-02 days |
03 | Forwarding of company’s proposal to Processing Team | 03 days |
04 | Scrutiny of Proposal by Processing Team | 07 days |
05 | Submission of proposals before Evaluation Committee, meeting of Evaluation Committee and issuance of meeting minutes | 15-30 days |
06 | Evaluation Committee recommendations to the relevant section post its meeting | 05 days |
07 | Approval of Evaluation Committee minutes from CEO, AEDB | 02-03 days |
08 | Letters to qualified/ unqualified companies for submission of certification fee and other fees as per Regulations or communication of score card to unqualified firms | 03 days |
09 | Timeframe provided to company to meet the requirements. | 07 days |
10 | Confirmation of BG & Payments by Finance Section | 07 days |
11 | Approval & issuance of certificate | 03 days |
Total number of days | 55-70 days |
Reference
- Submission of proposals before the Evaluation Committee depends upon the number of proposals.
- In case if there are shortcomings, these shortcomings are communicated to company for addressing and re-submission of proposal to AEDB within 15 days.
- Days mean working days.